The new surface has now a waterproof layer to promote drainage with layers of rock on top. The rock is larger on the bottom and will switch to a smaller size.

To begin the week of June 13th, the new scoreboard beams were set in deep holes and secured with concrete. Additionally, the new bleacher concrete base is being set and work conti...

In the past two weeks, there has been significant progress on the construction of the complex. These include finishing stabilization-laser grading, collecting old pipes, installin...


This is a view from the bottom prior to sand blasting the stadium and stabilization of the field.

After just one week, what was the previous athletic complex is completely unrecognizable. The clearing of the structures and scraping of the field went smoothly. With the dry wea...