March 12, 2024
WE ARE MOVING IN! The concession stand equipment is coming in daily, and picnic tables are being assembled. Every day, we get closer to the finish line. We want to say a huge th...

January 9, 2024
Do you want to help name the new building at the MCHS Riverview Stadium Plaza?
CLICK HERE FOR MORE INFORMATION!!

January 9, 2024
Do you want to help name the new building at the MCHS Riverview Stadium Plaza?
CLICK HERE FOR MORE INFORMATION!!

January 9, 2024
The Mount Carmel High School Riverview Stadium Plaza has come to light. The gates, graphics, painting, and remaining finishing touches are almost complete. Additionally, the fi...

November 6, 2023
We now have additional lights at Riverview Stadium! These lights will illuminate the entire Plaza area and walk paths. They are specially designed to concentrate light in their ...

November 14, 2022
RIVERVIEW STADIUM PLAZA - BE PART OF IT! Riverview Stadium, home of the Golden Aces, is steeped in history and family tradition. Your 8"x8" brick will become a permanent part ...

October 11, 2022
I am happy to announce that Phase 1 construction at the athletic complex is now complete. Phase 1 involved a new eight lane track, turf playing field, fencing, visitor bleachers,...

September 3, 2022
Another essential component of the renovation of the Riverview Stadium is the lights. The new lights are state-of-the-art LED lights that immediately illuminate. A cool feature ...

August 30, 2022
This week, the top dressing is being applied to the track. This application has a red brick color that maintains well in the sun and does not easily stain. Once the dressing set...

August 23, 2022
Progress continues on the many renovations to the athletic complex. Last week, the new scoreboard was installed. This scoreboard is not only much larger, but it also houses the ...

July 30, 2022
This week, MCPU installed new lights at the top of the stadium that will provide light on the steps and seating areas. Additionally, these LED lights will be on every night to p...

July 25, 2022
Today, July 25th, is the last day for turf installation, and the field look fantastic. Soon, the teams will be able to use the field. In the coming days, expect to see the light...

July 12, 2022
Asphalting began on Tuesday, July 12th, and will continue into Wednesday. The first layer is for a strong base, and a second thin layer will be applied for precision. This is th...

June 21, 2022
The new surface has now a waterproof layer to promote drainage with layers of rock on top. The rock is larger on the bottom and will switch to a smaller size.

June 14, 2022
To begin the week of June 13th, the new scoreboard beams were set in deep holes and secured with concrete. Additionally, the new bleacher concrete base is being set and work cont...

May 30, 2022
In the past two weeks, there has been significant progress on the construction of the complex. These include finishing stabilization-laser grading, collecting old pipes, installi...


May 19, 2022
This is a view from the bottom prior to sand blasting the stadium and stabilization of the field.

May 9, 2022
After just one week, what was the previous athletic complex is completely unrecognizable. The clearing of the structures and scraping of the field went smoothly. With the dry we...